SOCAR GPC - Gas Processing & Petrochemical Complex (GPC)

General Information
Owner Socar Gpc
Masterplan Project (Parent Profile)
Location Baku, Absheron, Azerbaijan
Status --
Sector Chemical, Production, Petrochemical Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $5700m
Award Date January 0001
Completion Date January 0001
Last Updated On January 2024
ProjectId (Old, New) 38364, 140461


The State Oil Company of Azerbaijan Republic's (SOCAR) is planning a gas processing and petrochemical complex (GPC), covering an area of approximately 4,500ha, will be located near Sangachal terminal, along the boundaries of the Absheron and Garadagh Districts, approximately 60km south of Baku.

The new complex is expected to replace the existing processing facilities in Baku and Sumgait. The products from the complex will primarily meet the domestic demands and the excess will be exported. The capacity of the complex will be around 10 billion cubic meters of gas per year.

The US$17,000 million project includes the following:

Phase 1:

1. Construction of a gas processing plant with a capacity of 12 billion m3 (BCM)

2. Construction of a petrochemical plant

3. Construction of 850,000 TPA integrated steam cracker unit

4. Construction of polypropylene and polyethene unit

5. Construction of a 250 MW thermal power plant

6. Construction of a 600,000TPA polyethene unit

7. Construction of a 610,000TPA ethylene pyrolysis plant

8. Construction of a 130,000TPA propylene plant

9. Construction of 32,000TPA Butene-1 and 21,000TPA Hexen-1 plants

10. Construction of a 42,000 TPA benzene plant

11. Construction of a 25,000 TPA gasoline plant

12. Construction of associated facilities

Phase 2:

1. Construction of diesel hydro-treatment unit

2. Construction of isomerization unit

3. Construction of methyl tertiary-butyl ether

4. Construction of fluid catalytic cracking gasoline treatment

5. Construction of sour water stripper

6. Construction of amine treatment unit

7. Construction of a sulphur recovery unit

8. Construction of new hydrogen (H2) production unit

9. Construction of new Bitumen Blowing Unit

10. Construction of associated facilities

Revamp:

1. Construction of crude and vacuum distillation unit

2. Construction of fluid catalytic cracking unit

3. Construction of continuous catalytic reforming unit

4. Construction of associated facilities

Second Section

12 January 2024

GPC: Petrochemical Plant Phase I, GPC: Phase 1: Gas Processing Plant: The projects continue to be on hold and the time frame for their revival is unknown at this juncture.

17 July 2023

GPC: Phase 1: Gas Processing Plant: The project continues to be on hold and the time frame for its revival is unknown at this juncture.

07 June 2023

GPC: Central Utilities Off Sites: The project continues to be on hold and the time frame for its revival is unknown at this juncture.

11 April 2023

GPC: Petrochemical Plant Phase I, GPC: Phase 1: Gas Processing Plant: The projects continue to be on hold and the time frame for their revival is unknown at this juncture.

19 September 2022

The project is put on hold and the revival is unknown at this juncture.

13 March 2022

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

03 August 2021

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

22 February 2021

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

28 August 2020

GPC: Phase 1: Petrochemical Plant: Main contract is yet to be awarded

28 August 2020

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

21 May 2020

GPC: Phase 1: Petrochemical Plant: The project is still under bid evaluation and the time frame for the main contract award is unknown at this juncture.

20 November 2019

Bids are still under evaluation.

26 July 2019

Bid evaluation is underway and the following joint venture companies have submitted bids for Petrochemical Plant Phase I: (1) A joint venture between Tecnicas Reunidas SA, Hyundai Engineering & Construction Co Ltd and Technip; (2) A joint venture between NIPIneftegas, Samsung Engineering Co Ltd and Tecnimont SpA;

03 May 2019

The main contract tender has been issued and the bid evaluation process is underway. We are in the process of identifying the bidders.

21 February 2019

Technip, Axens, Sinopec Tech, and Univation are the companies providing technology and licenses for the project.

26 November 2018

Tender has been issued for Phase I gas processing plant main contract and it is expected to award in September 2019.

18 September 2018

GPC: Central Utilities Off Sites (CUOS) and Phase 1: Petrochemical Plant: Tenders are not yet issued.

07 June 2018

Design activities are underway.

30 March 2018

Dutch ING Bank, the China Development Bank (CDB) and the Russian Gazprombank are the financial advisors and CDB bank is the main creditor for the project.

28 November 2017

Design activities are underway.

02 June 2017

GPC: Central Utilities Off Sites (CUOS) China Huanqiu Contracting and Engineering Corporation, subsidiary of China National Petroleum Corporation and Technip Italy have signed a service agreement for the preliminary detailed design work on the project.

15 May 2017

SOCAR signed a MoU with HQC and Technip Italy for the preliminary detailed design work of gas processing plant and polyethylene petrochemical complex.

04 January 2017

SOCAR awarded a series of contracts to Technip to deliver technology licensing and design work for petrochemical complex and LNG recovery for the gas processing plant.

13 May 2011

SOCAR announced plans to build the Oil and Gas Processing and Petrochemical Complex project in Azerbaijan.