SATORP - Amiral Complex: Utility Flare and Interconnection: Package 4

General Information
Owner Saudi Aramco Total Refining and Petrochemical Co
Masterplan Project (Parent Profile) SATORP – Amiral Complex – Eastern Province
Location Jubail, Eastern Province, Saudi Arabia
Status --
Sector Chemical, Production, Petrochemical Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 41
Estimated Budget Value ---
Contract Value 2500
Net Value $2500m
Award Date June 2023
Completion Date December 2027
Last Updated On September 2025
ProjectId (Old, New) 47615, 297885


Saudi Aramco Total Refining and Petrochemical (SATORP) is planning to undertake the construction of Utility Flare and Interconnection: Package 4 at Jubail II complex, Saudi Arabia.

The US$2500 million project includes the following:

1. Construction of buildings

2. Installation of flare stack & flare tip

3. Installation of utility systems

4. Installation of interconnecting systems

5. Construction of control & monitoring building

6. Installation of safety systems

7. Associated facilities

Second Section

19 September 2025

The construction works are ongoing on the project and are expected to be competed by the end of 2027.

02 January 2025

The construction works are still ongoing and are expected to be competed by the fourth quarter of 2027.

10 October 2024

The construction works are ongoing on the project.

01 July 2024

China Eleventh Chemical Construction Company has been appointed as the sub-contractor with a contract value of US$272 million for the project. (Source: MEED)

05 June 2024

Sendan International is working as the MEI Subcontractor and the construction works are ongoing on the project.

27 March 2024

The construction works are ongoing on the project and are expected to be completed by 2027 and the subcontractor has not yet been appointed.

09 November 2023

The detailed engineering works are still ongoing and the construction works have not yet commenced on the project. The project is expected to be completed by 2027.

04 July 2023

Hyundai Engineering & Construction Co. Ltd has been awarded the main contract for the project.

24 May 2023

Hyundai Engineering & Construction has been awarded the contract however the official announcement is still awaited.

16 March 2023

Hyundai Engineering & Construction has been awarded the contract however the official announcement is still awaited.

14 February 2023

The main contract is expected to be awarded in third or fourth week of March 2023. (Source: MEED)

11 January 2023

The main contract bids are still under evaluation and are expected to be awarded by March 2023. (Source: MEED)

16 December 2022

The client has taken the final investment decision for the construction of the complex.

25 November 2022

Hyundai Engineering & Construction has come up as the lowest bidder on the project. (Source: MEED)

15 November 2022

The main contract bids are still under evaluation and the time-frame for the award is currently unknown.

20 October 2022

Bids are under evaluation and Technip, Tecnicas Reunidas and Saipem amongst others have submitted bids.

12 October 2022

Hyundai E&C amongst others have submitted the commercial bids.

20 September 2022

Hyundai E&C amongst others have submitted the technical bids.

13 September 2022

The technical bid submission date has been extended till September 18, 2022.

24 August 2022

The technical bid submission date has been extended till September 11, 2022 and the commercial bid submission is on October 09, 2022. (Source: MEED)

14 July 2022

The bid submission date has been extended till August 31, 2022. (Source: MEED)

13 June 2022

The main contract tender is issued on project. The bids are expected to be submitted by August 15, 2022. Hyundai E&C, Saipem, Mc Dermott, Técnicas Reunidas, Sinopec, CPECC, CTCI, L&T, Samsung, JGC and Technip have prequalified companies on the project.

14 April 2022

The main contract tender is yet to be issued for the project.

24 November 2021

The project is facing delays.

29 September 2021

There is no news regarding the main contract PQ shortlist yet. Amongst others, CTCI, Hyundai E&C, Tecnicas Reunidas have submitted EOI for the project.

20 June 2021

The client has issued SOI for the project on April 22, 2021 and the expression of interest (EoI) documents have been submitted by May 30, 2021. (Source: MEED)

11 April 2021

FEED works are ongoing on the project and the main contract tender is yet to be issued.

02 June 2020

FEED works are getting delayed

10 April 2020

FEED works are progressing as per the schedule and the time frame for completion is unknown at this juncture.

10 December 2019

FEED works are ongoing and Saudi authority in talks with potential companies for further development. (Source: MEED)

23 October 2019

McDermott International has been appointed as the technology provider.

24 July 2019

TechnipFMC and WorleyParsons have been appointed as the FEED and PMC contractors respectively