SATORP - Amiral Complex: Utility Flare and Interconnection: Package 4
Saudi Aramco Total Refining and Petrochemical (SATORP) is planning to undertake the construction of Utility Flare and Interconnection: Package 4 at Jubail II complex, Saudi Arabia.
The US$2500 million project includes the following:
1. Construction of buildings
2. Installation of flare stack & flare tip
3. Installation of utility systems
4. Installation of interconnecting systems
5. Construction of control & monitoring building
6. Installation of safety systems
7. Associated facilities
Second Section
No Content
No Content
19 September 2025
The construction works are ongoing on the project and are expected to be competed by the end of 2027.
02 January 2025
The construction works are still ongoing and are expected to be competed by the fourth quarter of 2027.
10 October 2024
The construction works are ongoing on the project.
01 July 2024
China Eleventh Chemical Construction Company has been appointed as the sub-contractor with a contract value of US$272 million for the project. (Source: MEED)
05 June 2024
Sendan International is working as the MEI Subcontractor and the construction works are ongoing on the project.
27 March 2024
The construction works are ongoing on the project and are expected to be completed by 2027 and the subcontractor has not yet been appointed.
09 November 2023
The detailed engineering works are still ongoing and the construction works have not yet commenced on the project. The project is expected to be completed by 2027.
04 July 2023
Hyundai Engineering & Construction Co. Ltd has been awarded the main contract for the project.
24 May 2023
Hyundai Engineering & Construction has been awarded the contract however the official announcement is still awaited.
16 March 2023
Hyundai Engineering & Construction has been awarded the contract however the official announcement is still awaited.
14 February 2023
The main contract is expected to be awarded in third or fourth week of March 2023. (Source: MEED)
11 January 2023
The main contract bids are still under evaluation and are expected to be awarded by March 2023. (Source: MEED)
16 December 2022
The client has taken the final investment decision for the construction of the complex.
25 November 2022
Hyundai Engineering & Construction has come up as the lowest bidder on the project. (Source: MEED)
15 November 2022
The main contract bids are still under evaluation and the time-frame for the award is currently unknown.
20 October 2022
Bids are under evaluation and Technip, Tecnicas Reunidas and Saipem amongst others have submitted bids.
12 October 2022
Hyundai E&C amongst others have submitted the commercial bids.
20 September 2022
Hyundai E&C amongst others have submitted the technical bids.
13 September 2022
The technical bid submission date has been extended till September 18, 2022.
24 August 2022
The technical bid submission date has been extended till September 11, 2022 and the commercial bid submission is on October 09, 2022. (Source: MEED)
14 July 2022
The bid submission date has been extended till August 31, 2022. (Source: MEED)
13 June 2022
The main contract tender is issued on project. The bids are expected to be submitted by August 15, 2022. Hyundai E&C, Saipem, Mc Dermott, Técnicas Reunidas, Sinopec, CPECC, CTCI, L&T, Samsung, JGC and Technip have prequalified companies on the project.
14 April 2022
The main contract tender is yet to be issued for the project.
24 November 2021
The project is facing delays.
29 September 2021
There is no news regarding the main contract PQ shortlist yet. Amongst others, CTCI, Hyundai E&C, Tecnicas Reunidas have submitted EOI for the project.
20 June 2021
The client has issued SOI for the project on April 22, 2021 and the expression of interest (EoI) documents have been submitted by May 30, 2021. (Source: MEED)
11 April 2021
FEED works are ongoing on the project and the main contract tender is yet to be issued.
02 June 2020
FEED works are getting delayed
10 April 2020
FEED works are progressing as per the schedule and the time frame for completion is unknown at this juncture.
10 December 2019
FEED works are ongoing and Saudi authority in talks with potential companies for further development. (Source: MEED)
23 October 2019
McDermott International has been appointed as the technology provider.
24 July 2019
TechnipFMC and WorleyParsons have been appointed as the FEED and PMC contractors respectively