Saudi Aramco - Shedgum and Uthmaniya Gas Compression Program: Uthmaniya Gas Compression Plant: Package 10

General Information
Owner Saudi Aramco
Masterplan Project (Parent Profile) Saudi Aramco – Shedgum and Uthmaniya Gas Compression Program – Eastern Province
Location Saudi Arabia
Status --
Sector Gas, Downstream, Gas Processing Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 2240
Net Value $2240m
Award Date June 2026
Completion Date December 2028
Last Updated On August 2026
ProjectId (Old, New) 49251, 319073


Saudi Aramco is planning to undertake the construction of the gas compression plant work project at Shedgum and Uthmaniya gas compression program in Saudi Arabia.

This project will install advanced compression technology to raise the pressure of raw Khuff gas, enabling enhanced delivery into the processing and transportation systems. It will upgrade existing facilities at Shedgum and Uthmaniya, which currently receive about 870 million and 1.2 billion cubic feet per day of Khuff raw gas, respectively.

The aim is to significantly increase the compression and processing capacity of both plants while adding new pipelines to improve gas transport. Key components include a full EPC scope for the Uthmaniyah compression package, new compressor trains, mechanical and electrical works, and high-integrity pipelines. The intended outcome is improved operational efficiency, greater gas throughput, and strengthened energy supply infrastructure.

The scope of the Saudi Arabian project includes the supply of five electric motor-driven centrifugal compressor trains, together with associated balance-of-plant equipment and auxiliary systems. The compression facilities are intended to support production optimization and enhanced recovery, contributing to the extension of the field’s operational life. Baker Hughes will supply nine electric motor-driven compressor trains for a mature offshore field in the Middle East.

The US$2240 million project includes the following:

1. Construction of gas compression plant

2. Additions and Modifications to Shedgum and Uthmaniya gas plants to support the modified and new facilities

3. Modifications to compression stations

4. Modifications to gas booster stations

5. Installation of pumps, air coolers and heat exchangers

6. Installation of compression systems and associated infrastructure

7. Installation of safety & security systems

8. Construction of associated facilities

Second Section

13 August 2026

Saipem Nasser Saeed Al-Hajri Contracting Company (SNSH), a joint venture of Saipem and Nasser Saeed Al-Hajri & Partners Company for Contracting, has kicked off the EPC works on the project. (Source: MEED)

07 August 2026

The Saipem & Nasser Saeed Al-Hajri Contracting Company has awarded Baker Hughes for compressor supplier contract, Under the contract nine electric motor-driven compressor trains will supply.

12 June 2026

A joint venture of Saipem and Nasser Saeed Al-Hajri and Partners Company has been appointed as the main contractor for the project.

15 February 2026

The main contract bids have been submitted. We are in the process of identifying the bidders. (Source: MEED)

07 December 2025

The main contract bids are expected to be submitted December 07, 2025. (Source: MEED)

03 December 2025

The main contract bids are expected to be submitted by December 2025. The following companies are expected to submit the main contract bids on the project. Larsen & Toubro, Saipem, Nasser S Al Hajri Corporation, Tecnicas Reunidas, GS Engineering & Construction, Petrofac, Hyundai E&C and Samsung E&A.

14 November 2025

The main contract tender has been issued with a bid submission deadline of November 17, 2025. (Source: MEED)

06 April 2025

The main contract tender is not yet issued.

05 August 2024

The main contract tender is yet to be issued on the project.

14 March 2024

The main contract tender is not yet issued on the project.

10 January 2024

The main contract tender is not yet issued.

02 November 2023

The main contract tender is not yet issued.

24 August 2023

The main contract tender is not yet issued.

15 June 2023

The main contract tender is not yet issued.

30 March 2023

Market sources indicate that there is no news on the main contract tender issue date yet.

17 January 2023

ITB is not yet issued on the project.

12 May 2022

ITB is not yet issued on the project.

10 March 2022

Feed works are progressing and the project is expected to be awarded by 2023. (Source: MEED)

15 September 2021

Feed works are progressing and there is no news for the tender issue yet.

03 June 2021

Market sources indicate that the main contract tender has not been issued yet due to the ongoing situation in the country.

09 November 2020

ITB is not yet issued and the time frame for same is unknown at this juncture.

18 August 2020

The main contract tender has been cancelled and the time frame for new ITB is unknown at this moment.

10 June 2020

The project is under bid evaluation and the time frame for main contract award is unknown at this juncture.

10 April 2020

Bid evaluation is underway and the time frame for main contract award is unknown at this juncture.

25 February 2020

The bid submission has taken place on February 16, 2020, and SEPCO amongst the few others has submitted the bids.

10 February 2020

The bid submission date has been further extended to February 16, 2020.

05 February 2020

The bid submission date has been extended to February 9, 2020.

19 January 2020

ITB has been issued with the bid submission due on January 30, 2020. SEPCO amongst the few other companies is likely to submit the bids.