SABIC Agri Nutrients - San VII Ammonia & Urea Complex (Horizon 1)

General Information
Owner SABIC Agri Nutrients Company
Masterplan Project (Parent Profile)
Location Jubail, Eastern Province, Saudi Arabia
Status --
Sector Chemical, Production, Fertilizer Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 3470
Net Value $3470m
Award Date September 2026
Completion Date December 2030
Last Updated On September 2026
ProjectId (Old, New) 420790, 420790


SABIC Agri-Nutrients is undertaking the construction of the San VII Ammonia & Urea complex in Jubail Industrial City, Jubail, Saudi Arabia.

The San VII / Horizon 1 project, launched by SABIC Agri-Nutrients in oil-rich Jubail Industrial City with the original aim of building a low-carbon ammonia and urea complex—providing around 1.2 million tonnes per annum of blue (i.e., CO2-captured) ammonia alongside 1.1 million tonnes of urea and specialty agri-nutrients—to help Saudi Arabia accelerate its sustainable energy and agricultural goals under Vision 2030. The project secured feedstock allocation from the Ministry of Energy and includes state-of-the-art carbon capture, reforming technologies, and a green hydrogen electrolyzer.

However, in March 2026, SABIC announced a strategic reversal: the blue ammonia / low-carbon intent has been dropped in favor of a conventional ammonia-urea complex. Under the revised design, the seventh ammonia and urea facility will produce roughly 1.2 MMTA of conventional ammonia and about 2.6 MMTA of urea. This shift significantly increases urea capacity—with output rising from approximately 4.8 to 7.4 million tonnes annually—reflecting evolving considerations of feedstock availability, cost, market demand, and regulatory environment. The project remains important as a regional fertilizer hub to meet surging domestic and export demand, stabilizing food supplies and reinforcing Saudi Arabia’s role in global agricultural supply chains.

The facility will feature a 1.2 million metric ton annual capacity ammonia plant utilizing KBR technology, alongside two urea plants with a combined annual yield of 2.6 million metric tons licensed from Nextchem (Stamicarbon) and thyssenkrupp Uhde. Alignment with the group’s decarbonization targets is secured through the integration of a large-scale carbon capture unit powered by Shell Global Solutions technology, which will significantly minimize operational emissions intensity.

The US$3,470 million project includes the following:

1. Construction of an ammonia plant with an annual production capacity of 1.2 million metric tons

2. Construction of two urea plants with a combined annual production capacity of 2.6 million metric tons

3. Construction of bulk off-site loading and storage (ammonia tanks not certified blue, vapour control)

4. Construction of processing units for standard urea and commodity agri-nutrients (granular, prilled forms)

5. Construction of distribution units (road/rail/sea export facilities, bagging, bulk)

6. Installation of hydrogen compressors (for internal synthesis gas and ammonia refrigeration)

7. Construction of a carbon capture unit

8. Replacement of three flare headers (standard code flame arrestors)

9. Installation of valves (industrial spec: process and safety valves, no low-leakage special certification)

10. Laying of pipelines (for feed gas, ammonia, steam, cooling water)

11. Mechanical & instrumentation works (standard control systems; no carbon-capture monitoring)

12. Construction of associated auxiliary facilities (administration, maintenance, workshops, wastewater control)

Second Section

17 September 2026

NextChem has secured a US$144 million technology contract from the client to provide its NX STAMI Urea technology package and proprietary equipment for the development of the project. (Source: MEED)

10 September 2026

The Final Investment Decision (FID) has been approved and Samsung E&A has been appointed as the main contractor on the project with a contract value of US$ 3,470 million. Construction works are expected to commence by the fourth quarter of 2026 and expected to be completed by the fourth quarter of 2030.

29 June 2026

The Final Investment Decision (FID) is expected to be finalized soon and the main contract tender is yet to be awarded.

30 March 2026

The client has shifted the project from low-carbon (blue) ammonia to a conventional ammonia (1.2 MMTA) and urea (2.6 MMTA) facility, boosting urea capacity by 54%.

23 March 2026

The client has requested the bidders to extend the bid bond validity to August 26, 2026.

10 February 2026

The main contract tender is yet to be awarded on the project.

31 December 2025

The main contract tender is yet to be awarded.

07 October 2025

The main contract bids are still under evaluation.

31 August 2025

The main contract bids are still under evaluation.

13 August 2025

The main contract tender is expected to be awarded by September 2025.

05 June 2025

The main contract tender is yet to be awarded.

16 March 2025

Samsung E&A is the frontrunner for the engineering procurement and construction (EPC) contract however client still in discussion with the bidders. (Source: MEED)

25 February 2025

The main contract is not yet awarded.

04 February 2025

The main contract tender is yet to be awarded on the project.

04 November 2024

The main contract is yet to be awarded.

27 August 2024

The main contract is yet to be awarded.

25 July 2024

The main contract is yet to be awarded.

10 June 2024

The main contract tender has not yet been awarded on the project.

17 April 2024

The main contract bids were submitted on March 31, 2024, The following companies have submitted the bids 1. Larsen & Toubro, 2. A JV of JGC Corporation, Hyundai E&C, Toyo Engineering Corporation. 3. Samsung Engineering. Daelim has declined to bid for the project.

21 February 2024

The main contract bid submission has been extended from January 31, 2024, to March 31, 2024.

27 December 2023

The bid submission due has been extended till January 31, 2024.

19 October 2023

The FEED + EPC tender has been issued and the submission is expected to take place by the end of December 2023. L&T, JGC Corporation, Samsung Engineering, Daelim, Toyo, and HDEC are the pre-qualified companies.