QatarEnergy - North Field West Development: Downstream
QatarEnergy is planning to undertake the development of the North Field West project in Ras Laffan Industrial City (RLIC), Qatar.
The project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains.
The US$8,000 million includes the following:
1. Construction of two mega LNG processing trains
2. Construction of utilities & offsite facilities
3. Construction of helium recovery unit
4. Construction of non-technical buildings
a. Construction of warehouses
b. Construction of workshops
5. Construction of the administration building
6. Construction of other associated facilities
Second Section
No Content
No Content
26 February 2026
A consortium of Technip Energies, Consolidated Contractors Company and Gulf Asia Contractor has been appointed as the main contractor for the project. (Source: MEED)
17 December 2025
The Front End Engineering Design works are progressing and Technip Energies has been working as the FEED consultant on the project.
01 October 2025
The pre-FEED works are still ongoing on the project and the construction works are expected to be commenced by 2027.
26 May 2025
The pre-feed works are ongoing and the construction works are expected to be commenced by 2027 on the project.
22 January 2025
The final investment decision has been made for the development of the project. Currently, the pre-feed works are ongoing on the project and FEED contractor is yet to be awarded for the project.
19 December 2024
We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.
28 February 2024
The project is in the initial stages. (Source: MEED)