ADNOC Onshore - AiP5 Production Enhancement Plan: Bab & North East Bab Tie-In Facilities
ADNOC Onshore is planning to undertake the construction of the Bab & North East Bab Tie-In facilities project in Abu Dhabi, the UAE.
The One Tie-In project at the Bab and North East Bab field developments is integral to Adnoc Onshoreâs contribution to its parent company Adnoc Groupâs objective of achieving an oil production capacity of 5 million barrels a day (b/d) by 2027 â a campaign known as Accelerated Integrated Programme 5.
The project aims is to establish infrastructure in accordance with the NEB P5 directive, focusing on Al Nouf, Rumaitha, and Shannayel facilities. Crude oil extracted from these locations is directed to MP-21 before being transported to export terminals at Jebel Dhanna and Fujairah. The Al Nouf (Dabbâiya) field is situated in a coastal or shallow marine area, while the Rumaitha/Shanayel structures are located onshore near the southwestern coast of Abu Dhabi. The project encompasses the development of both on-plot (CPP) piping systems and off-plot clusters, pipelines, and trunklines.
Adnoc Onshore has divided the scope of work on the Bab and North East Bab One Tie-In project into 18 packages, which are as follows:
The US$1200 million project includes the following:
Bab asset:
Package 1: Off-pad â Demolition and construction of existing oil-producing wells as per the high hydrogen sulphide (H2S) standard package.
Package 2:Off-pad â Construction of new oil-producing wells as per the high H2S standard package.
Package 3:On-pad â Demolition and construction of existing oil-producing wells as per the high H2S standard package.
Package 4:On-pad â Construction of new oil-producing wells as per the high H2S standard package.
Package 5:On-pad â Construction of facilities at mini-pad, pad or well bay for tie-in of new oil-producing wells as per high H2S standard package.
Package 6:Off-pad â Construction of new oil-producing wells (low H2S) as per standard package.
Package 7:
A. Construction of water supply, disposal and injection wells as per standard package;
B. Construction of off-pad water injection wells;
C. Construction of on-pad water injection wells and water injection manifold.
Package 8:Off-Pad â Digitalisation of existing wells.
Package 17:
A. Well bay: On-pad wells, flowline, common facilities (PSS, CI skid, WHCP), overhead line
B. Mini-pad: On-pad wells, transfer line, blow down header, common facilities (PSS, manifold-OIL, MPFM, CI SKID, WHCP, drain oil network, pig launcher, receiver, potable water system), overhead line
C. Off-pad: Gas lift oil producer well
D. On-pad: Gas lift oil producer;
E. Electrical submersible pump (ESP) well: on-pad;
F. ESP well: off-pad.
North East Bab asset:
Package 9:Cluster-based â Construction of new oil-producing wells at Al-Nouf.
Package 10:Cluster-based â Construction of new water alternating gas (WAG) injection wells at Al-Nouf.
Package 11:Remote â Construction of oil-producing wells.
Package 12:Remote â Construction of WAG wells.
Package 13:Cluster-based â Construction of oil-producing wells at Rumaitha and Shanayel.
Package 14:Cluster-based â Construction of WAG wells at Rumaitha and Shanayel.
Package 15:Cluster-based â Construction and/or modifications of oil production/test manifold, gas injection/gas test manifold, let down gas manifold, well head control panel, gas supply connection for injection, gas supply connection for gas lift. Chemical injection skid, water injection manifold, maintenance flare package. Installation of new pig traps, installation of a hot tap and extension of the cluster plot.
Package 18:
Al-Nouf cluster: Common facilities (ETR, ITR, vent stack, overhead line, oil manifold, test manifold, gas lift manifold, drain oil tank, common pipe rack, etc.), gas lift oil producer wells, WAG injection wells;
Rumaitha cluster: Common facilities (ETR, ITR, vent stack, overhead line, oil manifold, test manifold, gas lift manifold, drain oil tank, common pipe rack, etc.), gas lift oil producer wells, WAG injection wells.
Bu Hasa asset:
Package 16:Off-pad â Digitalisation of existing wells.
Second Section
No Content
No Content
29 May 2026
The following companies have submitted the revised commercial bids for the project: Galfar Engineering & Contracting, Jereh, Kalpataru Projects International Limited, Matrix Construction, Robt Stone ME LLC, and Target Engineering. (Source: MEED)
11 January 2026
The expression of interest (EOI) has been issued with the interests submitted in December, 2025. (Source: MEED)
05 December 2025
ADNOC Onshore plans to execute the on-plot facilities package under a conventional EPC model and is expected to reissue the main contract tender by the end of this year. The client had previously received main contract bids in the second quarter, but later cancelled them. (Source: MEED)
05 May 2025
The bids are under evaluation. China Petroleum Engineering & Construction Corporation, Robt Stone and few other companies have submitted bids for the project.
09 February 2025
The main contractor is not yet awarded.
01 April 2024
The main contract tender has been issued and the bid submission deadline is in April 2024. However, the exact date is unknown at this juncture. Robtstone and a few other unknown companies are likely to submit bids. Currently, we are in the process of identifying the other pre-qualified companies. The project is expected to be completed by the end of 2027. (Source: MEED)