Saudi Aramco - COUR: Gas Compression Facilities: Phase IV

General Information
Owner Saudi Aramco
Masterplan Project (Parent Profile) Saudi Aramco – Commercialisation of Unconventional Resources: Jafurah – Eastern Province
Location Khobar, Eastern Province, Saudi Arabia
Status --
Sector Gas, Transmission, Gas Compression Station
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 1500
Net Value $1500m
Award Date June 2026
Completion Date December 2029
Last Updated On August 2026
ProjectId (Old, New) 443675, 443675


Saudi Aramco is planning to undertake the construction of a gas compression facility, phase IV, in Saudi Arabia.

The development involves two gas compression trains, each with a capacity of 200 million cubic feet per day. Key facilities include processing of inlet gas, handling of condensate and produced water, utilities such as nitrogen generation, potable and raw water services, chemical injection, and systems for flare gas recovery. It also includes the construction of support infrastructure such as firewater, sanitary, stormwater, potable, and raw water systems.

The US$1,500 million project includes the following:

1. Construction of two gas compression trains, each of 200 million cf/d capacity, measuring 400 by 400 metres

2. Construction of gas compression plant inlet area

3. Construction of gas compression plant condensate and produced-water handling facilities

4. Construction of outside battery-limit buildings, including all infrastructure located within the gas compression plant footprint, while excluding security buildings

5. Construction of a nitrogen generation unit

6. Construction of raw and potable water utilities

7. Construction of chemical injection systems

8. Installation of diesel systems

9. Installation of flare and flare gas recovery systems

10. Construction of gas compression plant burn pit

11. Installation of the closed drain system and oily water system

12. Installation of a sanitary water system

13. Installation of the stormwater system and firewater system

14. Installation of the fire and gas protection system

15. Instrumentation and plant air unit

16. Construction of other associated plant facilities and utility networks

Second Section

24 August 2026

Larsen & Toubro Energy Hydrocarbon (L&TEH) has been appointed as the main contractor. (Source: MEED)

13 June 2026

Larsen & Toubro Energy Hydrocarbon (L&TEH) has been selected as the main contractor for the development of the project and has commenced the EPC works. However, the official contract award and the final investment decision (FID) are yet to be made. (Source: MEED)

23 April 2026

The main contract bids are still under evaluation. Larsen & Toubro Energy Hydrocarbon and China Petroleum Engineering and Construction (CPECC) have emerged as lowest bidders for the project. The project is expected to reach the Final Investment Decision(FID) soon. (Source: MEED)

19 February 2026

The main contract bids are still under evaluation.

07 January 2026

The main contract bid bond validity has been extended till February 2026 on the project. (Source: MEED)

24 October 2025

The main contract bids are still under evaluation.

15 September 2025

The main contract bids are still under evaluation and the project is expected to be awarded by the end of 2025.

17 August 2025

The main contract bids are still under evaluation for the project.

11 June 2025

The main contract bid bond validity has been extended till September 2025 on the project. (Source: MEED)

21 April 2025

The main contract bids are under evaluation.

16 February 2025

The main contract bids have been submitted on January 15, 2025 and the following companies have submitted the bids: JGC Corporation, Larsen & Toubro Energy Hydrocarbon, Samsung E&A and Tecnicas Reunidas / Sinopec Group. (Source: MEED)

08 November 2024

The main contract bid submission date has been extended to December 31, 2024. (Source: MEED)

31 July 2024

The main contract tender has been issued for the project. The technical bid submission is expected to be submitted on October 15, 2024, and the commercial bid submission is on October 31, 2024 for the project. The following companies have submitted the EoI documents for the project: JGC Corporation, Larsen and Toubro Energy Hydrocarbon, Samsung E&A, Tecnicas Reunidas, and Sinopec Group. (Source: MEED)

04 April 2024

The client has has issued the solicitation of interest (SoI) for the project and the main contract tender is expected to be issued by September 2024. The following companies have expressed their interest for the project: JGC, L&T, Samsung Engineering, Saipem, Hyundai E&C, Tecnicas Reunidas, Tecnimont, GS Engineering. (Source: MEED)