Anesrif - Algiers - Tamanrasset Railway Line

General Information
Owner Agence Nationale d'Etudes et de la Realisation des Investissements Ferroviaires
Masterplan Project (Parent Profile)
Location Algiers, Algiers Province, Algeria
Status --
Sector Transport, Infrastructure, Railway
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $0m
Award Date December 2026
Completion Date June 2029
Last Updated On July 2026
ProjectId (Old, New) 473963, 473963


Agence Nationale d’Études et de la Réalisation des Investissements Ferroviaires (ANESRIF) is undertaking the construction of a 2,039 km Algiers-Tamanrasset railway line in southern Algeria.

The project is part of the Trans-Saharan Highway, which crosses six countries (Algeria, Mali, Niger, Nigeria, Chad and Tunisia) and connects Algeria to the rest of the continent

The project is also called "The Trans-Desert Railway".

Loan Agreement Reference: 2000300001577

Project Identification Number: P-DZ-DC0-003

The project is divided into three main sections

Section 1: Ouargla and In Salah Railway Line

Section 2: In Salah – Tamanrasset Railway Line

Section 3: Tamanrasset-In Guezzam Railway Line

The US$20,400 million project includes the following:

1. Construction of Ouargla and In Salah Railway Line

a. Algiers to Laghouat (308 km)

b. Laghouat to Ghardaïa (265 km)

c. Ghardaïa to El Meniaa (230 km)

d. El Meniaa to In Salah (420 km)

2. Construction of In Salah – Tamanrasset Railway Line (650 km)

3. Construction of Tamanrasset-In Guezzam section (400km)

4. Construction of main structural facilities such as viaducts, tunnels, stations, junctions, and major crossings across all sections

5. Installation of mechanical, electrical, and plumbing systems in stations and operational buildings

6. Laying of tracks throughout all sections between Algiers and Tamanrasset, including the border segment

7. Construction of road overpasses and road works in conjunction with railway alignment, including road-rail intersection structures

8. Construction of drainage works including culverts, pipe crossings, and installations for managing water flow and desert sand hazards

9. Installation of signalling systems and safety systems to ensure operational reliability and safety for both freight and passenger traffic

10. Installation of telecommunications, power supply, and other support infrastructure to maintain continuous operations in remote zones

11. Construction of associated facilities including resettlement-action infrastructure, station services, freight yards, and necessary administrative and logistic support

Second Section

28 July 2026

Ghardaia to El Meniaa Railway Line: US$878 million has been secured from the African Development Bank (AFDB) for the development of the project.

29 March 2026

The main contract tender has been issued, and the bid submission date is May 24, 2026. (Source: MEED)

05 February 2026

Laghouat-Ghardaïa & Ghardaïa-El Menea Railway Line: The consultancy tender has been issued on February 04, 2026, and the bid submission deadline is on June 09, 2026. Also construction and supervision of works tender will be issued on February 11, 2026 and the bid submission deadline is on June 14, 2026, and the main contract tender is expected to be issued on February 17, 2026 and the bid submission deadline is on May 10, 2026 and expected to be awarded by June 30, 2026.

06 January 2026

Laghouat-Ghardaïa & Ghardaïa-El Menea Railway Line: The African Development Bank (AfDB) has approved a US$875 million loan for the project's development.

04 September 2025

The main contract tender is expected to be issued soon, and pre-construction arrangements have been formalised.

25 May 2025

Study works are progressing on the project.

20 December 2024

The National Agency for Studies and Monitoring of Railway Investment is preparing the technical and feasibility studies for the project. The studies for nearly 1,084-km of rail line have been finished and the remaining part will be ready soon.