EWEC - Al-Nouf 1 Combined Cycle Gas Turbine (CCGT) IPP 3300 MW
Emirates Water & Electricity Company (EWEC) is undertaking the construction of a combined-cycle gas turbine independent power plant (IPP) at the Al Nouf Complex, Emirate of Abu Dhabi, UAE.
The facility will deliver approximately 3,300 megawatts (MW) of net generation capacity. Key components include high-efficiency gas turbines, seawater cooling systems, and supporting infrastructure for reverse osmosis desalination. While constructed without immediate carbon capture, the plant is designed to be carbon-capture-ready, allowing retrofits later to capture over 90% of CO2 emissions. Its intended purpose is to supply large-scale power with flexibility and reliability, supporting Abu Dhabiâs energy transition, renewable integration, and grid stability. The project is notable for being the largest single-site carbon-capture-ready CCGT plant in the UAE and will follow the Independent Power Producer model.
The project is located at the Al-Nouf complex, 30 kilometres southwest of the city of Abu Dhabi.
The US$3,300 million project includes the following:
1. Installation of gas turbines
2. Installation of heat recovery steam generators
3. Installation of steam turbine generators along with air coolers
4. Construction of gas storage facilities
5. Construction of combustion chambers
6. Construction of powerhouses
7. Construction of substations
8. Construction of a cooling tower
9. Laying of transmission lines
10. Installation of generators
11. Installation of command and control systems
12. Installation of related facilities
Second Section
No Content
No Content
31 March 2026
The following companies have submitted the bids for the development: *Consortium of Al Jomaih Energy and Water, Sembcorp, and Electricite de France, *Consortium of Engie, Korea Overseas Infrastructure & Urban Development Corp, and Korea Western Power, * Consortium of Korea Electric Power Corporation, and Etihad WE, and *Sumitomo Corporation.
23 February 2026
The main contract bids are expected to be submitted soon. The timeline of bid submission deadline is unknown at this moment.
03 November 2025
The following companies are expected to submit the main contract bids: 1. SEPCOIII Electric Power Construction Corporation 2. Samsung C&T Corporation and 3. China Energy Engineering Corporation.
23 July 2025
The developer tender has been issued and the bid submission deadline is in August 2025. The contract is expected to be awarded in December 2025.
11 July 2025
Siemens amongst other companies has submitted the statements of qualifications (SOQ) documents for the project.
15 April 2025
Emirates Water & Electricity Company (Ewec) has received statements of qualifications (SoQs) to develop the project. (Source: MEED)
26 March 2025
The client has extended the SOQ submission deadline from March 20, 2025, to March 28, 2025. (Source: MEED)
12 March 2025
Emirates Water & Electricity Company (Ewec) has issued a request for statements of qualifications (SOQs) from firms for a contract to develop the project and interested developers are expected to submit their SOQs by March 20, 2025. Ewec aims to issue the request for proposals before the end of March 2025, and the estimated bid submission deadline will be in late August 2025. The project is expected to reach commercial operations by June 2029. (Source: MEED)
