ADNOC - Project 5.0 Rich Gas Development Project: Habshan 7 New Gas Processing Train: Phase 3
ADNOC Gas Processing is planning to undertake the construction of a Habshan 7 new gas processing train project in Abu Dhabi, the UAE.
The gas processing plant having a capacity of 670 MMSCFD.
Habshan 7 project is the third phase of the Rich Gas Development capital expenditure programme by Adnoc Gas.
The US$4000 million project involves the following:
1. Construction of a new high-pressure pipeline
2. Construction of the separation and condensate stabiliser unit
3. Installation of acid gas removal unit
4. Installation of mercury removal unit
5. Construction of a deep NGL recovery unit
6. Installation of sales gas and residue gas compressor
7. Construction of NGL product storage and transfer pump
8. Installation of utility units
a. Installation of Instrument Air (IA) System
b. Installation of Nitrogen (N2) System
c. Installation of Potable Water (PW) System
d. Installation of Fire Water (FW) System
e. Installation of Steam Generation System
f. Installation of Demineralized (DM) Water System
9. Construction of the flare unit
10. Installation of flare gas recovery package
11. Construction of water treatment package
12. Construction of non-process buildings
13. Installation of power generation system
14. Construction of NGL pipeline
15. Construction of sales gas pipeline
Second Section
No Content
No Content
18 February 2026
The client has received the revised commercial proposals from contractors, and the bids have been submitted on February 06, 2026. (Source: MEED)
10 February 2026
The final investment decision is expected to be made in the first quarter of 2026. (Source: MEED)
29 December 2025
The main contract commercial bids have been submitted and the bids are under evaluation.
26 November 2025
The main contract commercial bid submission deadline is due on December 10, 2025. (Source: MEED)
08 October 2025
The technical bids have been submitted on the project and the following companies have submitted bids: Enppi & Petrojet, Jereh, Larsen & Toubro Energy Hydrocarbon, Petrofac, Sinopec, and Wison Engineering. (Source: MEED)
28 September 2025
The deadline for submitting the technical bids has been extended to October 6, 2025. (Source: MEED)
26 August 2025
The main contractor tender has been issued and the following companies biding are Petrofac, Tecnimont, Samsung, Sinopec, L&T, CPECC, Petrojet /ENPPI in a consortium.
12 August 2025
The main contractor tender has been issued with the submission in mid September of 2025. (Source: MEED)
17 June 2025
The expression of interest (EoI) was issued in March, and the contractors have submitted their interests on April 8, 2025, Wood Group has performed the study & initial engineering design on the project. (Source: MEED)