EnBW/Acwa Power - Yanbu Green Hydrogen Hub
ACWA Power, in partnership with Energie Baden-Württemberg (EnBW), is planning to undertake the construction of the first phase of a green hydrogen hub in Yanbu, Saudi Arabia.
This is one of the region's major green hydrogen projects.
The project is an integrated, export-oriented complex; the hub will self-supply electricity from dedicated renewablesâ5 GW of wind and 5 GW of solarâsupporting large-scale electrolysis and downstream conversion. Phase-1 hydrogen production is stated at 400,000 tonnes per year, with hydrogen further converted into more than 2.2 million tonnes per annum (tpa) of green ammonia for international markets via a specialized export terminal. Desalination capacity is included to provide high-purity water for electrolyzers and process needs, while a 400 km transmission line will connect generation assets and balance power delivery. The program targets full operational capacity by 2030, aligning with regional decarbonization goals and the growing global demand for green molecules (hydrogen/ammonia) as fuels and industrial feedstocks.
The US$17,000 million project includes the following:
1. Construction of a 400,000-tpy green hydrogen hub with integrated ammonia conversion
2. Construction of a seawater desalination plant with demineralization and brine outfall
3. Construction of a 400 km high-voltage transmission line with substations, SCADA
4. Construction of 10GW renewable generation station including wind and solar
5. Installation of 4GW electrolyzer trains with rectifiers, compression, controls
6. Construction of ammonia and hydrogen storage tanks, loading, boil-off handling
7. Construction of associated facilities including utilities, workshops, laboratories, firefighting
Second Section
No Content
No Content
25 October 2026
Green Ammonia Complex : The Front-End Engineering Design (FEED) works are completed on the project. The main contract tender has been issued and the bid submission deadline is unknown at this juncture. Tecnicas Reunidas, Sinopec, Samsung E&A, Power China, China Energy Engineering Corporation, Larsen & Toubro and Chengda Engineering Company amongst other companies are expected to submit the main contract bids.
19 August 2026
Green Ammonia Complex: Electrolyser Plant: The Front-End Engineering Design (FEED) has progressed up to 80 percent, and the project is expected to be completed by 2030.
13 May 2026
Green Ammonia Complex: Electrolyser Plant: The Front-End Engineering Design (FEED) are ongoing and the project is expected to be completed by 2030.
29 January 2026
Green Ammonia Complex: Electrolyser Plant: Haldor Topsoe Company has been selected as the ammonia technology licensor for the project.
31 December 2025
Electrolyser Plant: The Front End Engineering and Design (FEED) works are progressing on the project and are expected to be completed by the third quarter of 2026.
02 October 2025
Kent has been appointed as the client's engineer to oversee the technical and design assurance during the Front End Engineering and Design (FEED) phase and to support the transition from FEED into the Engineering, Procurement and Construction (EPC) phase. (Source: MEED)
05 August 2025
Tecnicas Reunidas and Sinopec Guangzhou Engineering have been appointed as the FEED contractor with a contract period of 10 months for the project. Tecnicas Reunidas was undertaking the pre-FEED works. Once the FEED works are over, the joint venture will present an engineering, procurement and construction (EPC) proposal for the project.
24 July 2025
ACWA Power signed a joint development agreement with Energie Baden-Württemberg (EnBW) for the development of the project.