MoPW, Cameroon - Olama - Kribi Highway: Lot 2: Bingambo - Grandzambi (Section 1)

General Information
Owner Ministry of Public Works, Cameroon
Masterplan Project (Parent Profile) MoP Cameroon – Olama - Kribi Highway – South
Location South, Cameroon
Status --
Sector Transport, Infrastructure, Road, Interchange
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $85m
Award Date September 2025
Completion Date March 2028
Last Updated On March 2025
ProjectId (Old, New) 470065, 470065


Ministry of Public Works, Cameroon is undertaking the construction of the section of the lot 2 of Olama - Kribi Highway, in Cameroon.

Tender No. No. 078/AIOO/MINTP/CSPM-PFC/CCCM-TR/2024

The US$85 million project includes the following:

1. Construction of a 43 km highway from Bingambo - Grandzamb

2. Construction of 8 bridges along the rivers (Mougue, Mvile, Mbikiliki, Mashuer, Tchote, Guiyo, Lekoundje, Grandzambi) with a length of 0.290km

3. Construction of box culverts

4. Construction of Hydrohalic structures

5. Construction of pavement

6. Rock excavation and backfilling works

7. Preparatory works

8. Construction of earthworks

9. Construction of interchanges

10. Installation of signaling and safety systems

Second Section

21 March 2025

The main contract bids have been submitted and we are in the process of identifying the bidders.

05 November 2024

The main contract tender has been issued and the last date for bid submission is on November 22, 2024.