QatarEnergy - NGL-5 Project

General Information
Owner Qatar Energy
Masterplan Project (Parent Profile)
Location Mesaieed, Al Wakrah Municipality, Qatar
Status --
Sector Gas, Downstream, Gas Processing Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 36
Estimated Budget Value ---
Contract Value 0
Net Value $0m
Award Date October 2023
Completion Date June 2028
Last Updated On September 2025
ProjectId (Old, New) 414759, 414759


Qatar Energy is undertaking the development of NGL-5 in Mesaieed, Qatar.

The project involves the early site preparation works for NGL 5 in an area of approximately 800,000 m2 in the Mesaieed Industrial Complex on the south of the existing Qatar Energy Tank farm and Refinery, and north of the existing Station-S in Mesaieed, Qatar.

Reference No. GT23105000

The shoreline is approximately 2 km southeast of the construction site.

The US$2540 million project includes the following:

1. Early site preparation works

2. Construction of NGL platform

3. Construction of access roads

4. Construction of detailed engineering & procurement works

5. Construction of fencing and gates

6. Earthworks including excavation, backfilling, sub-grading, and grading

7. Installation of safety and security systems

8. Construction of other associated facilities

Second Section

19 September 2025

Main Package: Larsen & Toubro Energy Hydrocarbon has been awarded an Engineering, Procurement and Construction (EPC) contract for the development of the project and the expected to be operational by the second quarter of 2028.

08 September 2025

Main Package: Larsen & Toubro Energy Hydrocarbon has emerged as a front runner and the project is expected to be awarded by September 2025. (Source: MEED)

01 September 2025

Early Site Preparation Works: The project is complete.

25 July 2025

Main Package: The contractors have submitted revised commercial bids for the project.

28 June 2025

Main Package: Contractors have extended the validity of their technical bids for the project. Given that these bids are valid until the end of August and that the evaluation of commercial bids is currently in progress, it is anticipated that client will award the main EPC contract by the end of August. (Source: MEED)

19 June 2025

Main Package: The commercial bids have been submitted for the project. The following companies, amongst others, have submitted the bids: CTCI Corporation, Larsen & Toubro Energy Hydrocarbon, McDermott, Saipem, Samsung E&A, Tecnicas Reunidas, and Maire Tecnimont. Early Site Preparation Works: The construction works are still ongoing on the project.

21 May 2025

Early Site Preparation Works: The construction works are ongoing and are expected to be completed by June 2025.

12 January 2025

Early Site Preparation Works: The construction works are ongoing on the project and are expected to be completed by the first quarter of 2025. NGL-5: Main Package: The main contract tender has been issued and the technical bid submission is in February & the commercial bid submission is in May 2025. (Source: MEED)

22 December 2024

Main Package: The main contractor is not yet awarded.

18 July 2024

NGL-5: Main Package: The client has issued the expression of interest with an EOI submission on June 24, 2024. The following companies participated in the tendering process: CTCI Corporation, Larsen and Toubro Energy Hydrocarbon, McDermott, Saipem, Samsung E&A, Tecnicas Reunidas, and Tecnimont. (Source: MEED)

22 January 2024

NGL-5: Early Site Preparation Works: The construction works have commenced on the project.

31 October 2023

NGL-5: Early Site Preparation Works: Iris Construction and Trading has been appointed as the main contractor.

04 October 2023

NGL-5: Early Site Preparation Works: The main contract bids are under evaluation on the project.

01 August 2023

NGL-5: Early Site Preparation Works: The main contract bid has been submitted on the project. Al Jaber Engineering, Al Jaber trading and contracting & Al Balagh Trading & Contracting have submitted the bids for this project. We are in the process of identifying the other bidders on this project.

13 July 2023

NGL-5: Early Site Preparation Works: The main contract bid submission has been extended and is expected to be submitted on July 23, 2023.

23 June 2023

NGL-5: Early Site Preparation Works: The main contract tender was issued on June 12, 2023, and the bid submission is on July 09, 2023.