Diriyah Company - Diriyah Project: Diriyah 2: Northern Community: New Iconic Museum

General Information
Owner Diriyah Company
Masterplan Project (Parent Profile) DGDA – Diriyah Project: Diriyah II: Northern Community – Ar Riyad
Location Riyadh, Riyadh Province, Saudi Arabia
Status --
Sector Construction, Cultural, Museum, Library
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 455
Net Value $455m
Award Date December 2025
Completion Date March 2028
Last Updated On January 2026
ProjectId (Old, New) 421392, 421392


Diriyah Company is planning to undertake the construction of the Saudi Arabian New Iconic Museum with a total GFA of 45,000 sqm in the Northern Community as part of the Diriyah Gate Development Program phase 2 in Riyadh, Saudi Arabia.

The US$455 million project includes the following:

1. Construction of museum (GFA 45,000 m2)

2. Construction of conference hall

3. Construction of restaurants

4. Construction of car parking facility

5. Landscaping works

6. Construction of associated facilities.

Second Section

05 January 2026

The JV of Hassan Allam and Al Bawani has been appointed as the main contractor on the project.

10 October 2025

Diriyah Company has invited contractors to submit their best and final offers. (Source: MEED)

08 September 2025

The commercial bids were submitted on August 24, 2025 and the second post-tender clarification on commercial round is submitted on September 8, 2025.

06 August 2025

The commercial bid submission date has been extended from August 3, 2025, to August 17, 2025. (Source: MEED)

22 July 2025

The following companies have submitted the technical bids on the project - Nesma & Partners, Alec, UCC Holding, Modern Building Leaders, and the JV of Rowad Modern Engineering/Wadi Maramer Construction, JV of El Seif Engineering Contracting/China State Construction Engineering Corporation and the JV of Al Bawani/Hassan Allam Construction.

09 July 2025

The commercial bid submission has been extended from July 6, 2025, to August 3, 2025. (Source: MEED)

05 June 2025

The technical bid submission is June 12, 2025 and the commercial bid submission is July 6, 2025. (Source: MEED)

11 May 2025

The main contract tender was issued in April 2025, and the bid submission deadline is June 2025. The following companies have invited to bid for the or the project: Besix, Samsung, Nesma & Partners, ALEC, UCC, and MBL. (Source: MEED)

14 March 2025

The PQ documents have been submitted on the project.

25 February 2025

The deadline for submission of prequalification documents is extended from January 22, 2025 to February 26, 2025. (Source: MEED)

28 January 2025

The PQ documents have been submitted on the project.

22 January 2025

The prequalification tender for the main contract has been issued, and the deadline for submission of prequalification documents is on January 22, 2025. Al Bawani and Trojan General Contracting amongst others were invited. (Source: MEED)

22 August 2024

Market sources indicate that the project is under design stage.

11 June 2024

It is understood that the design works are progressing on the project.

16 February 2024

RFP is expected to be issued by Q2, 2024 and the bids will be submitted by Q3, 2024.

31 January 2024

It is understood that the project is in the design stage.

30 October 2023

It is understood that the project is in the design stage and we are in the process of identifying the design consultant for the project. RFP is expected to be issued in Q1 2024 and bids will be submitted in Q2 2024.