Dar Al Arkan - Trump Tower in Jeddah

General Information
Owner Dar Al Arkan Real Estate Development Company
Masterplan Project (Parent Profile)
Location Jeddah, Mecca Province, Saudi Arabia
Status --
Sector Construction, Residential, Apartments
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 531
Net Value $531m
Award Date November 2025
Completion Date December 2029
Last Updated On December 2025
ProjectId (Old, New) 449698, 449698


Dar Al Arkan Properties (a subsidiary of Dar Al Arkan) and SNASCO Holding, owned by Saleh Alsoraye, through a joint venture called Ibdaa Properties, are planning to undertake the construction of the Trump Tower ( Ex Lamborghini-branded residential tower and Ex Commendatore Tower) over an 11,928m2 area located on Jeddah Corniche Road, close to Al Nawras Square in Jeddah City, Saudi Arabia.

The US$531 million project includes the following:

1. Construction of a 47-story luxury residential building (200m high, 350 units)

- Fine Dining

- Cigar Lounge

2. Construction of retail units

3. Construction of parking facilities

4. Installation of elevators

5. Construction of swimming pool

6. Construction of the gym

7. Construction of Yoga zone

8. Construction of Trump Private Club

9. Construction of associated facilities

Second Section

05 December 2025

The enabling works have been completed on the project.

26 November 2025

Arabian Construction Company has been appointed as the main contractor with an approximate contract value of SAR2 billion ($531 million) on the project.

20 August 2025

The post-tender clarifications have been submitted on August 18, 2025. Soil testing and foundation works are ongoing on the project.

14 August 2025

The post-tender clarifications were issued on August 9, 2025, and submissions are due on August 14, 2025.

31 July 2025

The main contract bids are submitted in May 2025 and it is expected to be awarded soon. Market sources indicate that BEC Arabia, Arabian Construction Company, Nesma & Partners, Modern Building Leaders, Freyssinet, Saudi Binladin Group, China Civil Engineering Construction Corporation and Masah Specialized Construction amongst others have submitted the bids.

22 July 2025

Edrafor Emirates is the enabling contractor, Buruoj Engineering Consultant is the design consultant and PMC, Salah Zughaibi Engineering Consultant is the consultant on the project.

03 February 2025

Specialized Italian Foundation Company has been appointed as the enabling subcontractor and the works have started on the project. (Source: MEED)

11 December 2024

The design of the project has been revealed.

28 August 2024

The client has appointed Rothschild & Company to provide financial advisory service for the project.

03 July 2024

The project is still in the design stage.

19 April 2023

The project is still in the design stage.

28 June 2022

The project is under design stage and waiting for approvals from the ministry.

29 June 2021

The client has signed an agreement with Dar Al Arkan for the development of the project and the development works are expected to commence by the fourth quarter of 2021.

29 July 2020

Norm Architects has appointed as an architect for the project.

28 August 2018

The project is in the early stages of development.

15 October 2017

SNASCO announced to construct the Corniche Mixed-Use Tower project.