KJO - Dorra Field Development Program: Offshore and Onshore Facilities: Package 2B
Al-Khafji Joint Operations (KJO), jointly run by Kuwait Gulf Oil Co. (KGOC) and Saudi Arabiaâs Aramco Gulf Operations Co. (AGOC), is planning to undertake the development of a central gathering platform complex and processing facilities Package 2B at the Dorra Gas Field Development project in the Kuwait Neutral Zone in Saudi Arabia.
This Dorra Field Development Program, specifically Package 2B, covers the addition of several vital offshore installations, including central gathering, compression and auxiliary platforms, an accommodation platform, and connecting trunklines and cables to shore.
The offshore development projects for the Dorra field are operated by Al-Khafji Joint Operations (KJO).
The project uses advanced offshore platform systems, subsea pipelines, and electrical and communication cable networks. It aims to boost gas output to reduce reliance on imports, provide feedstock for power generation and petrochemicals, and support Saudi-Kuwaiti energy security. The field is estimated to contain large non-associated gas reserves and is expected to produce around 800 million cubic feet per day (mmcfd) of gas during this phase
The project is a part of the Dorra Field Development Program, Offshore and Onshore Facilities.
The US$3700 million project includes the following:
1. Construction of the central gathering platform complex and processing facilities
2. Construction of auxiliary utility platform topsides and structural jackets
3. Construction of accommodation platform quarters and main marine bridge
4. Construction of dedicated flare platform structures and tripod towers
5. Construction of structural bridge platforms linking the offshore complex
6. Installation of multi-shareholder gas and condensate export pipeline networks
7. Installation of produced water pipelines from CGP/AI-Zour to Al-Khafji
8. Installation of recovered MEG pipelines from Al-Khafji to CGP
9. Installation of control and power systems linking Al-Khafji onshore/offshore
10. Installation of centralized offshore control rooms at the accommodation platform
Second Section
No Content
No Content
19 August 2026
The Project Management Consultancy (PMC) bid submission deadline has been extended to September 07, 2026. (Source: MEED)
15 August 2026
A consortium of Larsen & Toubro Energy Hydrocarbon (L&TEH) and Saipem has been appointed as the main contractor. (Source: MEED)
03 August 2026
The client has revised the Project Management Consultancy (PMC) tender, and the submission deadline is due on August 17, 2026. (Source: MEED)
15 June 2026
The main contract tender is yet to be awarded.
02 April 2026
A consortium of contractor Saipem and Larsen & Toubro Energy Hydrocarbon (L&TEH) has emerged as the lowest bidder for the project. (Source: MEED)
12 March 2026
The main contract bids have been submitted and the following companies have submitted the bids: NMDC Energy, Hyundai Heavy Industries, Saipem, Larsen and Toubro Energy Hydrocarbon. (Source: MEED)
19 February 2026
The main contract bid submission deadline has been further extended to March 02, 2026.
02 February 2026
The main contract bid submission deadline has been further extended to February 16, 2026. (Source: MEED)
23 January 2026
The following companies have submitted the Project Management Consultancy (PMC) bids for the project: Fluor, KBR, Kent, Tecnicas Reunidas, Wood, Worley. (Source: MEED)
16 January 2026
The main contract bid submission deadline has been further extended to January 26, 2026. (Source: MEED)
04 December 2025
The main contract bid submission has been further extended to December 22, 2025 and the following companies bidding are NMDC JV with Hyundai, McDermott, Saipem and L&T. The tender for Project Management Consultancy (PMC) has been issued with a bid submission deadline by the first week of January 2026.
03 December 2025
The tender for Project Management Consultancy (PMC) has been issued with a bid submission deadline of December 15, 2025 and the following companies bidding are KBR, Tecnicas Reunidas, Fluor Corporation, Worley & Wood Group. The two companies have a great chance to win are Wood Group or Worley.
25 November 2025
The main contract bid submission deadline is due on December 8, 2025.
03 November 2025
The tender for Project Management Consultancy (PMC) has been issued with a bid submission deadline of November 24, 2025. (Source: MEED)
29 October 2025
The main contract bid submission has been further extended to October 31, 2025 on the project. (Source: MEED)
12 September 2025
The main contract bid submission has been further extended to September 27, 2025 on the project. (Source: MEED)
04 July 2025
The main contract bid submission has been extended to July 31, 2025 on the project. (Source: MEED)
20 March 2025
The main contract tender has been issued on the project with a bid submission date of June 30, 2025. The following companies are participating in the tendering process: Lamprell, Larsen and Toubro Energy Hydrocarbon, McDermott, NMDC Energy, and Saipem. (Source: MEED)
06 March 2025
The main contract tender has not yet issued on the project.
17 January 2025
Technip Energies Company is working as the FEED contractor and design works are ongoing.
11 July 2024
The project is in the initial stage of development.