ADNOC - Umm Shaif Gas Cap and Surface Pressure Boosting: Phase 1: Offshore Package I
ADNOC Offshore is planning to undertake the construction of a gas compression system for the Umm Shaif Gas Cap and Surface Pressure Boosting Development in the northwest of Abu Dhabi, the UAE.
This project enhances the Umm Shaif field by adding a gas cap and introducing surface pressure boosting systems to increase output. It uses large-scale compression technology, new wellhead towers, separation units and subsea pipelines to both capture associated and non-associated gas and raise condensate volumes.
The aim is to lift gas production by about 600 million cubic feet per day (cf/d) and raise condensate output by around 50,000 barrels per day, feeding approximately 520 million cf/d of the additional gas into the ADNOC Group sales grid. The outcome is a stronger gas supply, better reservoir pressure maintenance and improved recovery from the Khuff formations.
Offshore package 1 â fabrication of a 30,000-tonne gas compression system
The US$1570 million project includes the following:
1. Construction of offshore fabrication gas compression
2. Construction of topside modules & compression
3. Construction of a gas processing and separation platform
4. Construction of surface pressure boosting (SPB) platform
5. Construction of support platforms and modules and injection infrastructure
6. Installation of electrical, instrumentation, control, and safety systems
7. Installation of interconnects to existing production and processing infrastructure
8. Construction of associated offshore facilities
Second Section
No Content
No Content
27 August 2026
Technip Energies has been appointed as the detailed engineering services provider for the development of the project. (Source: MEED)
21 August 2026
Algihaz Marine Contractors is working as a sub-contractor on the project. (Source: MEED)
05 August 2026
A consortium of Larsen & Toubro and Lamprell has been appointed as the main contractor with a contract value of US$1570 million. (Source: MEED)
22 July 2026
The client has announced a US$ 6200 million final investment decision (FID) for the development of the project. (Source: MEED)
10 June 2026
The main contract bids are still under evaluation, and the following companies submitted the bids are: Saipem, Seatrium, Larsen & Toubro Energy Hydrocarbon, Lamprell, NMDC Energy, Hyundai Heavy Industries. the contractors that are understood to be in the lead are: Larsen & Toubro and Lamprell. (Source: MEED)
08 February 2026
The main contract commercial bids have been submitted on the project. (Source: MEED)
29 January 2026
The main contract commercial bids submission deadline has been further extended from January 26, 2026, to February 02, 2026. (Source: MEED)
08 January 2026
The main contract commercial bids submission deadline has been further extended from January 05, 2026, to January 26, 2026. (Source: MEED)
13 December 2025
The main contract commercial bids submission deadline is due on January 05, 2026. (Source: MEED)
23 November 2025
The main contractor bids have been submitted and the bids are under evaluation. (Source: MEED)
12 October 2025
The technical bids submission deadline has been extended to October 30, 2025. (Source: MEED)
10 September 2025
The timeline for the technical bids submission is further extended from September 01, 2025, to October 10, 2025. (Source: MEED)
03 August 2025
The main contractor tender has been issued in the first quarter of 2025 and the technical bids submission deadline is on September 1, 2025. (Source: MEED)