ADNOC - Bab Gas Cap: BGC Pipelines EPC 3
ADNOC Gas is planning to undertake the Laying of the Bab Gas Cap Pipelines in Abu Dhabi, the UAE.
Adnoc will hold the majority 60% stake in the Bab Gas Cap development and production concession, with TotalEnergies, BP, CNPC, Jodco Onshore, China ZhenHua Oil and Korea GS E&P collectively holding the remaining 40% interest
This initiative forms part of the Bab Gas Cap (BGC) development to link new processing plants with existing infrastructure. It includes the routing, fabrication and installation of multiple product pipelinesâparticularly for liquid sulphur transfer to the Habshan Granulation Plantâand sales gas and feed gas connections. Driven by modern pipeline engineering and ADNOCâs onshore pipeline standards, the project aims to secure safe, efficient transport of hydrocarbons, reduce flaring, and enable full utilisation of gas output. The ultimate intention is to support ADNOC Gasâ strategy to increase its gas processing capacity by about 20%âapproximately 1.8 billion standard cubic feet per dayâand thereby advance the UAEâs gas self-sufficiency and energy security.
The US$1000 million project includes the following:
1. Installation of sales gas pipeline 48' inch & length 18km from New BGC Plant to 2 x 52â @ KP30 HMT Pipelines
2. Installation of NGL pipeline 20' inch & length 54km from New BGC Plant to 30â MERAM (BVS-1) NGL Pipeline â Habshan Ruwais corridor
3. Installation of condensate pipeline 18' inch & length 54km from New BGC Plant to 24â existing condensate pipeline Habshan Ruwais corridor
4. Installation of nitrogen pipeline 10' inch & length 31km from the existing 48â MIRFA Habshan N2 Pipeline (Habshan) to the New BGC plant
5. Installation of a water pipeline 10-inch & length 27km from the existing TAQA DN1600 Water Pipeline to the New BGC plant
6. Installation of safety & security systems
7. Installation of hot tapping technology
8. Installation of a new receiver station for construction near the Maqta corridor
9. Installation of pig launcher for the new N2 pipeline
Second Section
No Content
No Content
22 September 2026
The technical bids have been submitted, and the following companies have submitted bids: Kalpataru Power Transmission, Sinopec, and C.A.T Group, China Petroleum Pipeline Engineering, Al Nasr Contracting Company, and Galfar Engineering & Contracting. The commercial bids are expected to be submitted by December 2026.
28 August 2026
The main contract tender has been issued and the submission deadline is unknown at this juncture. Target Engineering and China Petroleum Engineering & Construction Corporation (CPECC) amongst other companies will be submitting the main contract bids on the project.
11 August 2026
The client is in the process of finalising the final investment decision (FID) for the development of the project. (Source: MEED)
26 June 2026
The main contract tender is yet to be issued on the project. (Source: MEED)
24 April 2026
The contractors expressed the interest formed the following teams to compete in the main contract tendering round are as follows: Larsen & Toubro, Samsung E&A, Saipem, NMDC Energy, Technip Energies, JGC Corporation, Sinopec, Tecnimont, China Petroleum Engineering and Construction Corporation (CPECC), and the main contract tender is yet to be issued on the project. (Source: MEED)
24 February 2026
The contractors have submitted their expression of interest (EoI) on the project. (Source: MEED)
22 February 2026
An expression of interest (EoI) has been issued for the project. (Source: MEED)
21 October 2025
The Feed works are ongoing on the project and the main contract EOI has been issued in September for the project.
