ADNOC Offshore - Expansion of Upper Zakum Field Development: Package III

General Information
Owner ADNOC Offshore
Masterplan Project (Parent Profile) ADNOC Offshore – Expansion of Upper Zakum Field Development – Abu Dhabi
Location Abu Dhabi, Emirate of Abu Dhabi, UAE
Status --
Sector Oil, Upstream, Oil Extraction
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 5666
Net Value $5666m
Award Date June 2026
Completion Date December 2028
Last Updated On June 2026
ProjectId (Old, New) 556921, 556921


ADNOC Offshore is undertaking the development of the expansion of the Upper Zakum Offshore Field Development Package 3 in Abu Dhabi, the UAE.

This project leverages artificial islands, AI-enabled control systems, and clean-grid power to significantly boost oil production capacity in the Upper Zakum offshore concession. It aims to raise current output from around 1.0 million barrels per day to 1.5 million bpd.

The key components include new wellhead facilities, separation and processing units, utilities, water injection systems, pipelines, and modernization tie-ins. The outcomes will include greater reliability, reduced emissions through the use of cleaner energy and digital automation, enhanced reservoir recovery, and strengthened long-term production to support both domestic demand and export requirements.

This project is a part of the Expansion of the Upper Zakum Field Development

The US$5666 million project includes the following:

1. Installation of gas lift compression system

2. Installation of seawater intake pumps and filtration system

3. Installation of instrument air and air dryer packages

4. Installation of nitrogen generation and chemical injection packages

5. Installation of onshore pipeline and tie-ins

6. Upgradation of multiple decks at gas lift platforms

7. Construction of gas dehydration and vapour recovery units

8. Construction of electro chlorination package

9. Construction of pipe racks and modular rooms

10. Construction of storage facilities and infield pipelines

Second Section

15 June 2026

Tecnicas Reunidas has been appointed as the main contractor for the project.

07 June 2026

The bids are still under evaluation, and Tecnicas Reunidas is said to be the favourite to win the main EPC contract. (Source: MEED)

21 April 2026

The client is in final discussions to award the main contractor, and the main contract bids are still under evaluation.

16 March 2026

The main contract tender is not yet awarded.

29 January 2026

The commercial bids have been submitted on the project. Larsen & Toubro, Tecnicas Reunidas and Technip amongst other companies have submitted the bids.

09 January 2026

The main contract commercial bid submission deadline is due on January 15, 2026. (Source: MEED)