Al Yasat Petroleum Operations - Belbazem Full Field Development
Al Yasat Petroleum Operation (AYPO) ADNOCâs subsidiary and joint venture (JV) with China National Petroleum Corporation (CNPC), has planned to construct the Belbazem full field development project in Abu Dhabi, UAE.
Belbazen block field consists of three oil-bearing structures namely Belbazen to produce 45,000 Barrels per day (BPD) of oil and 27 mmcf (765,000m3) per day of gas.
The US$900 million project includes the following:
1. Drilling of 60 wells
2. Laying of pipelines
3. Construction of WHT with four spitters
4. Construction of fuel gas system
5. Construction of closed drain and open drain system
6. Construction of fuel as sweetening unit
7. Construction of switchgear room
8. Construction of battery room
9. Construction of telecom equipment room
10. Construction of LER and control room
11. Construction of new GTG package
12. Installation of power system
13. Installation of a vapour recovery system
14. Installation of instrument and utility air unit
15. Installation of a hot oil system
16. Installation of nitrogen system
17. Installation of cooling water units
18. Installation of flare (HP & LP)
19. Installation of utility water units
20. Installation of portable water units
21. Installation of firewater units
22. Installation of electrical substation
23. Installation of 132 Kv electrical tie-ins
24. Installation of telecommunication facilities
25. Installation of associated facilities
Second Section
No Content
No Content
28 March 2024
The project is completed.
20 February 2024
Finishing works are ongoing on the project and are expected to be completed by third quarter of 2024.
11 October 2023
CPEC is working as the MEI subcontractor and the construction works are ongoing on the project as per the schedule.
11 September 2023
Construction works are progressing and are expected to be completed by 2024.
12 June 2023
Construction works are progressing as per schedule on the project.
14 March 2023
Construction works are ongoing and the project is expected to be completed by the end of 2024.
12 December 2022
The construction works are ongoing on the project and is expected to be completed by July 2024.
08 April 2022
3W Networks has been awarded the contract for delivering telecommunication systems.
27 July 2021
NPCC has issued a tender for MEIC and Pipe spooling works on July 21, 2021 and the bid submission is due on August 15, 2021. (Source: MEED)
11 July 2021
National Petroleum Construction Company (NPCC) is in preliminary negotiation for the subcontract works with CPECC for the onshore scope. (Source: MEED)
01 June 2021
National Petroleum Construction Company (NPCC) is negotiating with Emirates Steel and other steel manufacturers for procuring its requirements for steel beams and other steel structures . (Source: MEED)
25 May 2021
National Petroleum Construction Company has been appointed as the main contractor with a contract value of US$744 million.
14 April 2021
NPCC has been emerged as the front runner.
28 February 2021
The project is not yet awarded and the time frame for main contract award is unknown at this juncture.
10 February 2021
The project is not yet awarded and the time frame for main contract award is unknown at this juncture.
20 January 2021
The project is yet to be awarded and the time frame for the same is unknown at this juncture.
17 December 2020
The project is not yet awarded and the time frame for same is unknown at this juncture.
03 November 2020
The project is not yet awarded and the time frame for same is unknown at this juncture.
21 October 2020
The project is not yet awarded and the time frame for same is unknown at this juncture.
22 September 2020
The project is not yet awarded and the time frame for same is unknown at this juncture.
14 July 2020
The project is not yet awarded and the time frame for same is unknown at this juncture.
07 April 2020
The main contractor is yet to be appointed and the time frame for same is unknown at this juncture.
20 February 2020
The project is yet to be awarded and the time for the same in unknown at this juncture.
05 December 2019
The bid evaluation is underway and the time frame for main contract award is unknown at this juncture.
20 November 2019
McDermott International has been emerged as the lowest bidder.
04 November 2019
The FEED activities are complete.
30 September 2019
FEED works are progressing as per the schedule and the time frame for completion is unknown at this juncture.
30 July 2019
FEED works are ongoing and there is no change in the completion date for FEED.
10 April 2019
The FEED activities are underway and expected to be completed by August 2019 post the evaluation of the FEED documents, the EPC contract would be awarded.
04 February 2019
Three Joint venture companies have been shortlisted for FEED contract and the selection of EPC is expected to be made in the next six months after submitting the EPC bids. The three groups are China Petroleum Construction Company, China Offshore Oil Engineering Company (COOEC) and Franceâs TechnipFMC, Abu Dhabi-based National Petroleum Construction Company (NPCC) with the UKâs Petrofac, US-based McDermott. (Source: MEED)
17 January 2019
The technical bids have been submitted for FEED contract, awaiting for pre-qualified companies list.
09 October 2018
The technical bid submission date has been further extended to October 14, 2018.
01 October 2018
The technical bid submission date has been extended to October 8, 2018.
05 September 2018
The tender for FEED has been issued on the project on September 4, 2018, and bid submission is expected on October 1, 2018. The following companies among others have received the tender. *L&T *Technip *Doris Engineering *Mcdermott
04 September 2018
Mcdermott has been awarded the Pre-feed on the project.
09 July 2018
The scope of the project has been revised and is limited to re-select and design basis only. The commercial bid submission for Pre-feed is expected on July 10, 2018. The following companies among others have submitted the technical bids for Pre-feed. *L&T *Doris Engineering *McDermott
12 April 2018
Technical Pre-feed tender for the project has been submitted in March 2018 for the project. Technip FMC has submitted the pre-feed tender. Market sources indicate that following companies have also participated in the Pre-feed tenders *Doris Engineering *L&T *McDermott The commercial FEED bid submission is expected by end of April 2018.